Extra work does not eat the margin, an unclear process does
During demolition a moisture damage appears in the intermediate floor that was not visible in the source data. At the same time the customer asks for a new socket and swaps the agreed tile for a more expensive model. The site manager wants to keep the site moving, so the crew carries on. The price is promised later.
This is an ordinary moment on a construction site. It is also the moment where profitable extra work can turn into work done for free.
The purpose of managing extra and variation work is not to slow the site down or turn every small deviation into a contract negotiation. The purpose is to make sure that, before the work is done, the parties understand what changes, what it costs and how the change affects the schedule.
When the process is clear, extra work can be handled quickly. The observation is documented, the impact is calculated, the customer approves the quote and the work moves into production. The same information follows later into the project's cost tracking and onto the invoice.

What is the difference between extra work and variation work?
In everyday talk extra work and variation work are often mixed up. For managing a project the distinction is still useful.
Extra work is a new item that does not belong to the originally agreed content. During a renovation the customer may, for example, order the painting of another room or new fittings that were not agreed at the start.
In variation work the original item changes. An agreed material is swapped, the method changes, or the scope grows because of new source information. A change can raise or lower the price and also affect the schedule.
In software both are best handled with the same basic process, but it is worth marking the type of work. That way, at the end of the project, estimation deviations in the original work can be separated from changes ordered by the customer.
Step 1: record the observation before the details are forgotten
Extra work often starts from a spoken request or an observation made on site. At this stage a complete quote is not needed yet, but a trace is.
A good first entry contains:
- what was observed or what the customer asked for
- in which room or work phase it came up
- when the observation was made
- who raised it
- photos or other documentation
- whether the work has to be paused while a decision is made
- the preliminary impact on work and schedule.
The entry is best made directly on the project. If the photo stays in a phone and the change is discussed in two message groups, it is hard to show later what the pricing was based on.
Speed matters more than precision here. The site manager can fill in the costs later, but the situation on site, the condition of the structure and the customer's original request are worth saving immediately.
In Fisas documentation an observation can carry the project details, a description, photos, a category and a status. That way the source data for an extra work quote is found in the same place as the rest of the site documentation.
Step 2: calculate the impact as whole work, not just material
The price of extra work is often underestimated because the most visible cost is the easiest to calculate. A new tap costs a certain amount, extra boards a certain amount, and a rental machine has a daily rate. The real impact of the work, however, consists of several parts.
Pricing should take into account at least:
- own labour and the related indirect personnel costs
- materials, freight and possible waste
- subcontracting
- equipment, protection and cleaning
- design and site management
- interruption of other work or a change in the work order
- schedule impact
- the company's overheads and target margin.
Take a simple example. The customer wants to move a partition wall that has already been built. The additional material cost is only 180 euros. The change, however, requires partial demolition of the finished frame, a new measurement, moving an electrical installation, boarding, filling and protecting the work area again. If the quote is based only on the extra material and a few visible working hours, the company pays for coordinating the change out of its own margin.
In the Fisas extra and variation work calculation, costs can be split into materials, own labour and subcontracting. Overheads and margin can be added to the calculation, so the price presented to the customer is based on the whole impact rather than a single purchase.
Step 3: get the content, price and impact approved in an understandable form
Approval is not just a yes. The customer has to be able to understand what they are approving.
An extra work quote should describe at least the content of the work, the boundaries, the price, VAT, the effect on the schedule and any effect on other work phases. If the exact quantity cannot be known in advance, the quote can agree on a unit price or an hourly basis and on how the actuals are reported.
The description is best written in the language of the site. "Opening structures to the extent required" leaves more room for interpretation than "opening the boarding of the bathroom's north wall over roughly two square metres in order to inspect the damaged frame". A precise description protects both parties and makes the invoice easier to check.
Electronic approval speeds up the decision, because the customer does not have to print, sign and return a document. At the same time the date, the approver and the approved content stay in the project data.
In Fisas an extra work quote can be sent to the customer by email. The customer opens the link in a browser, reviews the quote and approves it electronically. The approved version and the signature remain in the project's contract history.
What if the work has to be done immediately?
Situations arise on site where waiting would cause damage, a safety risk or an unreasonable delay. Even then it is worth separating the necessary protective measure from the actual extra work.
For example, a leak can be contained, the structures protected and the situation documented right away. The scope and price of the actual repair are approved afterwards. The entry records why the immediate action was taken, what was done and who was informed.
Situations like this underline the importance of photos, timestamps and message history. The system does not settle a contractual question on the company's behalf, but it makes sure the information behind the decision is preserved.