← Knowledge base

Cost estimation

Contract estimating: hourly cost, unit prices and risk allowance

7 July 2026 · 8 min read

What your own hourly cost is made of, how to derive unit prices from your own history, how big a risk allowance is justified, and how the estimate becomes the project budget.

Cost estimation on mobile

A good estimate is repeatable

Contract estimating is often seen as a matter of experience: a good estimator can price a job, a poor one cannot. Experience helps, but it explains only part of the difference. Two equally experienced estimators reach different figures if one has a structured way of working and the other does not. The same estimator reaches different figures on different days if nothing makes them go through the same points.

This article covers how to build the estimate: how to break a contract down, what your own hourly cost is made of, how to derive unit prices from your own history, how big a risk allowance is justified, and how the estimate becomes the project budget. Quote wording, price estimates and validity are covered in the article on accuracy and speed in quoting.

Break the contract down to the level hours are recorded at

The first decision is not what the work costs but how it is broken down. The breakdown decides what you can learn from the estimate afterwards. A contract priced as one sum only tells you in post-calculation whether the job was profitable. One priced by work phase tells you which phase was misjudged, and that improves every estimate after it.

The rule of thumb is to break the estimate down to the level at which hours are recorded. If hours are recorded against five work phases, there is no point in twenty rows in the estimate, because they cannot be compared with anything. On larger jobs it pays to follow an established classification, such as the Finnish Talo 2000 system, so estimates are comparable with each other and with the client's.

For a bathroom renovation, a breakdown that works is, for example:

  1. protection and demolition
  2. plumbing (subcontract)
  3. electrical (subcontract)
  4. building work: falls, levelling, waterproofing and tiling
  5. fitting fixtures and finishing.

Five rows are enough when hours are recorded against the same five.

Quantities are where most errors happen

Most estimating errors are quantity errors, not pricing errors. The unit price can be right and the result still a third out if the area is wrong. Quantity errors have three common sources.

A measurement is misread. The wrong scale, an old revision, or units that change partway through a drawing.

An item is left out. The most common and most expensive error. The estimate looks complete, so checking it does not reveal what is missing. You only notice by comparing with something: a previous similar job, or a checklist that is the same every time.

The same item is counted twice. Less common, but usual when the estimate has been built in several sittings.

Measuring quantities directly from the drawing, so that the source of every quantity is visible, removes the first error and reduces the third. Against the second, standard assemblies help, with the usual parts of a work phase already included rather than left to memory.

Your own hourly cost: where 40 euros comes from

Many small contractors price labour at their charge-out rate without knowing exactly what a worked hour costs them. The hourly cost has three parts.

Wage. For example 23.50 euros an hour.

Employer costs and paid absences. Pension and social security contributions, insurance, holiday pay, holiday bonus, public holidays and sick pay. Spread over hours actually worked, these typically raise the wage by a factor of about 1.6 to 1.8 in Finnish construction. With a factor of 1.7, a worked hour costs about 40 euros. The exact factor is worth working out once with your accountant from last year's figures.

Overheads. Van, tools, insurance, office, phones and software. They are usually added as a percentage on top of direct costs, typically 5–10 percent in construction. Your own percentage comes from comparing the year's overheads with the direct costs of your projects.

With labour at 40 euros an hour and overheads at 8 percent, the cost price of an hour is about 43 euros. If the charge-out rate is 55 euros, labour leaves a margin of about 12 euros an hour, about 21 percent of the selling price. The figure is sensitive: if the real employer cost factor is 1.8 and overheads 10 percent, the margin drops to about 15 percent. That is why the factor and the overhead percentage are worth working out once from your own figures rather than estimating them.

Unit prices from your own history

General unit prices are an average across companies whose equipment, crew and methods differ from yours. They are a good starting point when you have no data of your own, and a poor one when you do.

To build your own unit price, it is enough to know the hours and quantities from three completed similar work phases. Three observations are not a statistically convincing sample, but they are far better than none, and they describe your own crew.

Look at the spread as well as the average. If the building work in three bathrooms took 55, 60 and 72 hours, the average of 62 does not tell the whole story. The interesting question is what made the third one different. The answer is usually in the conditions: an old building, a sloping floor, cramped space or poor access. That calls for a factor for difficult sites, not a new average.

A risk allowance is the price of uncertainty

The risk allowance is often dropped when the price needs to be competitive. But the allowance is the price of uncertainty. If something turns up under the structures of an old building, someone pays for it, and without an allowance that someone is the contractor.

Scale the allowance to what is known about the site. A reasonable starting point:

  • New build, familiar structures, good drawings: 0–3 percent.
  • Renovation, structures partly known: 5–10 percent.
  • Demolition or unopened structures: 10–15 percent, or a unit-price contract instead of a fixed price.

Adjust the percentages according to your own post-calculations. More important than the size is that the allowance is a visible row where the uncertainty lies, for example on the demolition row. An allowance hidden in unit prices disappears in post-calculation, and you no longer know whether the job was profitable or whether the allowance ate the result.

Try FiSAS for free, 14 days, no payment details.

Start trial

Ask for subcontract prices, do not guess

Subcontracts are often a third or more of the contract price, and they are the only part of the estimate you can get exactly without your own work. Yet they are estimated surprisingly often.

Ask in writing if the amount is significant. A price given over the phone changes more easily once the subcontractor sees the site.

Check what the price covers. Are materials, lifting and cleaning included? This is where understandings differ, and the difference only shows on site.

Add your own margin and coordination. Supervising the subcontract, scheduling it and getting faults fixed is work that belongs in the price.

If a subcontractor cannot give a price by the deadline, you can use the previous price with an allowance for change, or decline to quote. An optimistic guess is the worst option, because it both lowers your price and raises your risk.

The estimate becomes the budget

A well-made estimate produces three things, and only the first goes to the client: the quote, a budget to track actuals against, and a reference for the next estimate.

If the estimate does not become the project budget, tracking starts by guessing what was supposed to happen. If the estimate is not kept in a form that shows its assumptions, the next similar job is priced from scratch again. The third is what gets lost most often: the quote is in an email, the budget in someone's head, and the reference nowhere.

Post-calculation is the only point where estimating learns

When the contract ends, compare estimated and actual hours by work phase, see where the gap was largest, and write one sentence on why. That sentence is the whole value of the exercise. "Tiling took 30 percent longer than estimated because the old floor sloped and levelling was done twice" changes the next estimate. "Tiling went over" changes nothing.

Post-calculation gets skipped because the next contract is already running when one ends. What works is making it part of closing the contract: the final account is not done until one sentence on the deviation has been written.

The most common structural mistakes

  • Every estimate starts from scratch. The same work phase is priced again in every quote, and the result is slightly different each time.
  • An old quote is edited without checking its structure. The previous job's assumptions come along unnoticed.
  • Material prices are out of date. An estimate looks just as right with months-old prices as with current ones. Note the date the prices are from.
  • Margin is calculated differently each time. A 20 percent margin on the selling price means a price of 12,500 euros on a cost of 10,000 euros, and 20 percent on top of costs means 12,000 euros. Either works, as long as the same method is used every time and by every estimator.

How this works in FiSAS

In FiSAS an estimate does not start from scratch, and the same estimate carries on as the project budget:

  • Your own price lists and standard assemblies. Unit prices, margins and standard assemblies for work phases are saved once, and every quote builds on them. Materials, labour and subcontracting are in the same calculation.
  • Quantities from drawings. AI calculates areas, lengths and counts, and the drawing shows where each quantity comes from. You can also measure yourself by clicking, and quantities move into the quote without retyping.
  • From quote to budget. An accepted quote becomes a project whose budget is compared with actuals following the structure of the quote and by cost type: labour, materials, subcontracting and other. The company chooses its own tracking level: quote rows, cost codes or the top level, and time entries and purchase invoices can use different levels. That keeps the breakdown of the estimate and the level hours are recorded at the same.
  • Hours allocated as they are worked. Workers record hours on their phones against the project and the chosen tracking level, so the data for post-calculation builds up during the work.

Quoting and time tracking are included in every plan. Quantity take-off from drawings is in the Builder and Master plans.

Test your own situation

Can you say which work phase went over its estimate in your most recently completed contract, and why? If not, your estimating is not learning anything yet, and that is worth fixing before anything else.

FiSAS can be tried free for 14 days. You can price the next contract in it with your own unit prices, and when the job is done, see in the same place which work phase missed the estimate.

Try FiSAS for free

14 days, no payment details, no commitment.

Start free trial